Phase VII Water Line Extension to Valeene Update 06/29/2011
Water Main installation is complete. Final meters are being dropped in and turned on. The booster station is up and running and the tank is full. Everyone signed up for phase VII meters should have water or be getting it very shortly. Cleanup of the construction right-of-way is ongoing, slowed by wet weather. Expect cleanup and seeding to be complete by the end of July. Paving of the Valeene Road has started. It should be completed by mid July. All work should be done and over with around the end of July.




Thursday, June 30, 2011 at 1:45PM